| 1. Readiness gate | 100% of the order finished and at least 80% packed. If not, the visit may be postponed or reported as PENDING. |
| 2. Documents and gauges | MTCs, 100% factory test records, gauge ID and calibration validity; thickness gauge checked with foils before use. |
| 3. Quantity and random selection | Count cases and pieces against PO and packing list. The inspector — not the factory — picks the sample cartons for AQL. |
| 4. Markings | Body marks and nameplate to MSS SP-25 or EN 19 as the PO requires: maker, material, rating, size, heat number, flow arrow. |
| 5. Dimensions | Face-to-face, flange OD, bolt circle, hole diameter, raised-face diameter and facing finish against drawing and standard. |
| 6. Visual workmanship | Castings, sealing faces, paint runs, missing parts, bolt threads, bore cleanliness. Each defect classed critical, major or minor. |
| 7. Pressure test witness | Shell → backseat (if fitted) → high-pressure seat → low-pressure air seat, as the PO requires. Gauge, serial and timed hold recorded. |
| 8. Operation | Full open / close; smooth, no binding. Handwheel turns or operating torque against the drawing or data sheet; no gland leak after. |
| 9. Coating DFT and colour | Readings per sample at agreed points (body, bonnet, flange back); average and minimum recorded; shade checked against the RAL card. |
| 10. PMI (only if ordered) | Portable XRF on stem, body and seat overlay, verified against a check standard. Supports, never replaces, the MTC. |
| 11. Packing and ISPM 15 | Flange end covers fitted, valve position per spec, preservation, ISPM 15 mark on wood, shipping marks match the PO. |
| 12. Witness log and closing record | Facts explained to the factory; defect list acknowledged in writing. Report in English, normally within 24 hours. |