Home › Guides › ISO 2859-1 vs ANSI/ASQ Z1.4

ISO 2859-1 vs ANSI/ASQ Z1.4: how AQL sampling works on a valve inspection

The two sampling standards use the same tables for a single lot. This guide shows how inspection levels, defect classes and acceptance numbers work, gives the 6-step procedure an inspector follows on site, and explains why a coating reading is logged separately from visual AQL.

ISO 2859-1ANSI/ASQ Z1.4AQLPSI

Short answer: ISO 2859-1 and ANSI/ASQ Z1.4 are the two names buyers most often see for attribute sampling. For a single lot, inspected once under normal inspection, they use the same code-letter and acceptance-number tables. The purchase order still has to name the standard, the inspection level, the AQLs and how defects are classified — otherwise the factory and the inspector are guessing.

By Kevin Lyu (吕中国), ValveWitness Inspection, Ningbo · Published 2026-11-14

In our sample report: Sections 1 and 3 show a 300-piece lot sampled to ISO 2859-1 / ANSI/ASQ Z1.4, General Inspection Level II, sample size 50. Visual results were within the acceptance numbers (Critical 0, Major 2 against Ac 3, Minor 4 against Ac 5). The overall result is still PENDING because a material certificate was missing and one DFT sample was below the specified minimum — those are not visual AQL counts. See the sample report.

How ISO 2859-1 and ANSI/ASQ Z1.4 relate

Both standards descend from the same family of sampling tables (historically MIL-STD-105). ISO 2859-1 is the international standard for sampling by attributes; ANSI/ASQ Z1.4 is the widely used US counterpart. On a typical valve pre-shipment inspection of one lot, under single sampling and normal inspection, the same lot size and inspection level produce the same sample-size code letter, the same sample size, and the same acceptance (Ac) and rejection (Re) numbers for a given AQL.

They are not word-for-word identical. Switching rules between normal, tightened and reduced inspection, and some administrative wording, are where the documents differ. Those switching rules matter more for a series of lots from the same supplier than for a one-off PSI. If your corporate specification names Z1.4, write Z1.4; if it names ISO 2859-1, write ISO 2859-1. Do not treat a mix of names as a reason to invent a hybrid plan.

General Level II vs special levels S-3 and S-4

General Inspection Level II is the default when the order does not say otherwise. It is the level used for visual and workmanship checks in our sample report. Level I gives a smaller sample (less discriminating); Level III gives a larger sample (more discriminating).

Special levels S-1 to S-4 exist for checks that are time-consuming, require a gauge set-up, or are only needed on a smaller number of pieces — dimensional checks, coating thickness, or some laboratory tests. They produce a much smaller sample. In the sample report, dimensions and DFT were agreed at special level S-3. For a lot of 300 pieces, the single-sampling, normal-inspection tables give code letter D and a sample of 8 pieces.

Pressure-test witnessing is not automatically an AQL sample. Many buyers set a separate witness quantity in the ITP (20 pieces in the sample report) while the factory still tests 100% of the lot to the product or test standard.

Critical, Major and Minor defect classification

AQL is applied to classes of visual or workmanship defects, not to “the valve as a whole”. You need a written definition before the visit, usually in the ITP or inspection protocol:

  • Critical — a defect judged likely to be unsafe, or to stop the valve performing its primary function. Buyers commonly set AQL 0, which means any critical defect fails the lot.
  • Major — a defect likely to reduce usability or to be rejected by the end user (for example a scratch across the raised-face serration, or a sand inclusion of a stated size on a pressure-containing surface).
  • Minor — a defect that does not materially affect use (for example a paint run on the bonnet that does not leave bare metal).

The inspector counts defective units (or defects, if that is what the plan says) in the sample against the Ac/Re numbers for each class. If the number found reaches the rejection number, that class fails, and the lot fails.

Worked example: the sample report’s lot of 300

The figures below are the EXAMPLE plan printed in the sample report. They match the single-sampling, normal-inspection reading of the ISO 2859-1 / Z1.4 tables for that lot size. Always confirm Ac/Re from the edition named in your PO.

ParameterValue in the sample report (EXAMPLE)
Lot size300 pcs
Inspection level (visual / workmanship)General Inspection Level II
Sample size code letterH
Sample size (visual / workmanship)50 pcs
Special level for dimensions / DFTS-3 → code letter D → 8 pcs (client-defined)
Pressure-test witness quantity20 pcs (per the client ITP; the factory tests 100%)
Defect classAQL (EXAMPLE)AcReFoundResult
Critical0 (not allowed)010Conform
Major2.5342Conform
Minor4.0564Conform

Ac is the maximum number of defectives (or defects) that can be found in the sample and still accept the lot. Re is the number at which the lot is rejected. For these table cells, Re is Ac + 1.

6-step field procedure: how an inspector actually runs AQL on site

The tables are only half the job. This is the order in which we apply ISO 2859-1 / ANSI/ASQ Z1.4 at a valve factory, using the 300-piece lot from the sample report. The figures are the single-sampling, normal-inspection reading of the tables; exact cells must always be read from the buyer’s licensed edition of ISO 2859-1 or ANSI/ASQ Z1.4.

  1. Confirm the lot size (N) and the readiness gate. Count the finished units in the inspection lot — one PO line, one type and size, made under the same conditions (300 valves in the sample report). Random sampling is only representative when the lot is 100% finished and typically at least 80% packed. If half the valves are still on the assembly line, we report that and agree a new date or a DUPRO instead of sampling what happens to be ready.
  2. Select the inspection level. General Inspection Level II (G-II) is the default for visual and workmanship checks. Special level S-3 or S-4 is used for time-consuming gauge or instrument checks such as dimensions and coating DFT. Pressure-test witnessing and loading supervision are not taken from the AQL table: the witness quantity follows the PO or the client ITP (for example 20 pieces, or 100%), while the factory tests 100% of the lot to the product or test standard.
  3. Look up the code letter and the sample size (Table I → Table II-A). Table I gives the sample-size code letter from the lot size and the inspection level; Table II-A (single sampling, normal inspection) converts the letter into a sample size. For N = 300: G-II gives code letter H → 50 pieces; S-3 gives code letter D → 8 pieces.
  4. Read Acceptance (Ac) and Rejection (Re) numbers for each defect class. Each class has its own AQL column: Critical — commonly AQL 0, i.e. Ac 0 / Re 1, so any single critical defect fails the lot; Major — commonly AQL 2.5 (1.0 or 1.5 for stricter buyers); at n = 50, AQL 2.5 gives Ac 3 / Re 4; Minor — commonly AQL 4.0 (or 2.5); at n = 50, AQL 4.0 gives Ac 5 / Re 6.
  5. Follow the table arrows — the most common mistake. Where a code-letter row meets an AQL column at a downward or upward arrow instead of a number, follow the arrow to the first number shown, and use the sample size of that new row for that defect class. For example, at code letter D (8 pieces) the AQL 1.0 column normally points down to the row with Ac 0 / Re 1 and a sample of 13 pieces. Different classes can therefore end up with different sample sizes on the same lot. If the adjusted sample size equals or exceeds the lot size N, inspect 100% of the lot for that class. Always read the exact cells from the buyer’s licensed ISO 2859-1 or ANSI/ASQ Z1.4 tables — we do not reproduce the copyrighted tables here.
  6. Draw cartons across the whole lot, then count by unit. Samples are drawn from cartons spread across the entire lot — in the sample report, cases 2, 5, 9, 13, 17, 21 and 24 of 25 wooden cases — never from boxes the factory has pre-staged. Counting is unit-based and by worst defect: if one valve has 1 Major and 1 Minor defect, it is counted once, under Major, in the unit tally, and both defects are photographed and listed. Measured specification deviations — dimensions outside the drawing tolerance, coating DFT below the specified minimum, a missing EN 10204 3.1 MTC, or any leak on a pressure test — are logged separately and lead to PENDING or FAIL; they are never offset against the visual AQL totals.

Quick check for your PO: lot size and readiness gate · standard and inspection level (G-II, plus S-3/S-4 for measured checks) · AQL per class (Critical / Major / Minor) · witness quantity for pressure tests from the ITP · what happens on PENDING.

Why a measured specification deviation is logged separately

A visual AQL plan answers a different question from a measured test. Sand inclusions and paint runs are classified and counted. A coating-thickness average that falls below the specified minimum, or a dimension outside the drawing tolerance, is a specification deviation on that sample. In our sample report, the low DFT reading on sample S3 is listed in the defect list with the note that it is not counted in the visual AQL totals.

That is why a lot can be “within AQL” for workmanship and still not be a PASS. The measured check has its own acceptance rule, taken from the coating specification or the drawing, not from the AQL table.

PASS, FAIL and PENDING

Our reports use three overall conclusions:

  • PASS — every section conforms, and visual defects are within the AQL acceptance numbers.
  • FAIL — any critical defect, defects at or above a rejection number, or a failed pressure test.
  • PENDING — a final decision is needed from the client. Typical reasons are a missing document, a measured deviation outside the agreed checklist, or a required test that was not witnessed.

In the sample, visual results conformed, quantity, packing, marking, dimensions, operation and the witnessed pressure tests conformed, but the report is PENDING because the MTC for heat H2611-07 was not on site and one DFT sample was below the specified minimum. The client is asked to decide on shipment release.

What to write into the purchase order or ITP

  • The sampling standard (ISO 2859-1 or ANSI/ASQ Z1.4) and that inspection is single sampling, normal, unless you want tightened or reduced rules.
  • The inspection level for visual checks (General Level II unless you have a reason to change it) and any special level for dimensions or DFT (S-3 or S-4).
  • AQL values and written definitions for Critical, Major and Minor defects.
  • A separate rule for measured checks (dimensions, DFT, PMI) so they are not silently folded into the visual tally.
  • The pressure-test witness quantity, which may be independent of the AQL sample.
  • What should happen if the result is PENDING (hold shipment, re-work and re-inspect, or a written concession).

Sources

  • ISO 2859-1, Sampling procedures for inspection by attributes — Part 1: Sampling schemes indexed by acceptance quality limit (AQL) for lot-by-lot inspection — iso.org
  • ANSI/ASQ Z1.4, Sampling Procedures and Tables for Inspection by Attributes — ASQ
  • Our sample valve PSI report (fictitious data), Sections 1 and 3.
  • Pre-shipment inspection service page.

We report facts from the samples inspected. Standards named in these guides are public standards we work to, not certifications or accreditations we hold. We do not issue product certificates or accreditation marks. Test pressures, durations, leakage rates and acceptance numbers must be read from the licensed edition named in your purchase order; we do not reproduce copyrighted tables from the standards.

Related

PSI vs DUPRO vs test witness vs loading

What each inspection stage actually covers, why a late PSI can miss casting and dimensional faults under paint and crates, and how to write hold points into your PO.

Related

ISO 19840 vs SSPC-PA 2 and ISPM 15

ISO 19840’s 80/20 rule versus SSPC-PA 2 spots, a worked DFT example from the sample report, and what ISPM 15 marks and flange protection should look like.

Related

EN 10204 3.1 vs 3.2 and PMI

What 2.1, 2.2, 3.1 and 3.2 certificates actually mean, how heat numbers must trace to the body, and why XRF cannot measure carbon in WCB or L-grades.

Need an inspector at a Zhejiang factory?

Send your PO or specification, the factory city and the date. We confirm scope and price within one working day.

Request an inspectionWhatsApp +86 131 2757 0627